Delta State warns contractor over delays to Orere Bridge and Edjekota‑Ewu‑Orere road projects
Delta’s Commissioner for Works criticised a contractor for slow progress on the Orere River Bridge and the Edjekota‑Ewu‑Orere road, saying rain can no longer be used as an excuse and threatening to recommend sanctions.
By LAS News Desk · Published 31 Oct 2026, 23:47 WAT

Delta State authorities have formally cautioned the firm in charge of constructing the Orere River Bridge and repairing the Edjekota‑Ewu‑Orere route within Ughelli South Local Government Area. During an on‑site inspection on 31 October 2026, Commissioner for Works (Highways and Urban Roads) Reuben Izeze expressed strong displeasure with the pace of work, stating that the contractor’s presence on the sites was intermittent and that the rainy season could no longer be cited as a justification for delays.
Izeze told engineers accompanying him that the contractor appeared to engage in "window dressing" – making the sites look active only when ministry officials arrived – and warned that any further occurrence would lead to a recommendation for sanctions to the state’s leadership in Asaba. He stressed that the projects had already exceeded their expected timelines and that timely completion was essential for residents of the Orere and Ewu communities.
Background
Initially granted on 27 January 2021, the Orere River Bridge initiative, which features connecting roads and a spur in Orere Town, carried a contract price of N9.85 billion. Subsequent revisions increased the contract sum to N32.45 billion. Subsequently, the identical builder secured the contract for resurfacing and asphalt overlay of the Edjekota‑Ewu‑Orere road on 3 September 2026, valued at N6.92 billion. Mobilisation of the road works began on 10 September 2026, and the contract stipulated a completion date of 10 March 2028.
Both projects form part of the state’s broader effort to boost infrastructure and support indigenous contractors, a policy the administration has highlighted as a means to encourage local participation in development.
Why it matters
The delayed bridge and road works directly affect the mobility and economic activity of the Orere and Ewu communities, which rely on these routes for trade, health access and daily travel. Prolonged construction hampers the delivery of essential services and may increase transport costs for residents.
The state’s warning underscores the government’s intent to hold contractors accountable, especially those that have received significant backing under the indigenous‑contractor initiative. By threatening sanctions, the administration signals that financial and political support will be contingent on meeting agreed timelines and quality standards.
What happens next
Commissioner Izeze indicated that a further inspection could result in a formal recommendation to the governor’s office in Asaba for appropriate action against the contractor. No specific sanction has been detailed, but the warning suggests that the state may pursue contractual penalties or other administrative measures if progress does not improve before the next scheduled review.
The contractor has not publicly responded to the allegations, and the state has not announced any immediate changes to the project schedules. Monitoring of the sites is expected to continue, with the government emphasizing that future visits will assess genuine on‑site activity rather than superficial appearances.
Sources
Spotted an error? Report a correction · Corrections policy
Related stories

First Niger Bridge Reopens After 38‑Day Closure for Emergency Repairs
The federal government reopened the First Niger Bridge linking Onitsha and Asaba on 15 October 2026 after a 38‑day closure for emergency rehabilitation, following vandalised structural components and persistent rainfall delays.
LAS News Desk · 15 Oct 2026, 21:15 WAT · 3 sources

Lagos Bridge to Open Before Christmas After Steel Monument Delay
Governor Babajide Sanwo‑Olu confirmed the Opebi‑Odoiya Alaro Bridge will open to traffic before the holiday season, after delays caused by the installation of an 80‑per‑cent‑complete steel monument.
Photo: Ademola Olaniran / Wikimedia · CC BY-SA 4.0
LAS News Desk · 26 Oct 2026, 07:15 WAT · 4 sources

Lagos to divert traffic on Independence Bridge during three‑day asphalt repairs
The Lagos State Government has announced a three‑day traffic diversion on Independence Bridge as the Federal Ministry of Works carries out urgent asphalt resurfacing from 16 to 18 October 2026, with partial lane closures and LASTMA traffic management.
LAS News Desk · 15 Oct 2026, 21:45 WAT · 4 sources

New Yalu River Bridge opens after 12‑year delay, boosting China‑North Korea trade
The four‑lane New Yalu River Bridge linking Dandong and Sinuiju was formally opened on 15 October 2026, after remaining unused for a decade. The crossing is expected to ease freight traffic and support a revival of trade between the two neighbours.
Photo: Caitriana Nicholson from 北京 ~ Beijing, 中国 ~ China / Wikimedia Commons · CC BY-SA 2.0
LAS News Desk · 16 Oct 2026, 04:16 WAT · 5 sources

Nigeria moves to link Lagos‑Calabar Coastal Highway with East‑West Road as three‑year completion target set
Minister of Works David Umaha said the 750‑km Lagos‑Calabar Coastal Highway will be finished in just over three years and clarified that a new spur will connect it to the East‑West Road in Ondo, addressing earlier controversy over the route.
LAS News Desk · 24 Oct 2026, 06:15 WAT · 7 sources

Sokoto State Council greenlights over N21bn for roads, boreholes and hospital upgrades
The Sokoto State Executive Council approved projects totalling more than N21 billion, covering new and upgraded roads, solar‑powered boreholes and extensive hospital renovations, as announced by Governor Ahmed Aliyu and media director Abubakar Bawa.
LAS News Desk · 17 Oct 2026, 19:43 WAT · 2 sources
More Africa/Nigeria news ›
- FCT Minister Nyesom Wike Calls on Tinubu Supporters to Deliver Votes Ahead of 2027 Election
- Tompolo donates 30 vehicles as Osun leaders rally for Tinubu's 2027 re‑election
- Nigerian Navy Marines and Army Amphibious Brigade eliminate 34 Boko Haram fighters in Lake Chad operations
- Professor Amadike Ugbogu appointed as Abia State University’s ninth Vice‑Chancellor
- Federal technical team sent to Ogun to investigate recurring subsurface gas emissions affecting schools