The Nigerian government has secured the release of 98 containers of transmission equipment held at ports for nearly 20 years. The move aims to strengthen the national grid and reduce power outages.

By LAS News Desk · Published 7 Nov 2026, 22:17 WAT

Nigeria releases 98 containers of power equipment stranded for two decades
LAS News Africa/Nigeria graphic

The Federal Government of Nigeria has secured the release of 98 containers of high-voltage transmission equipment that had been stranded at the country’s ports for almost 20 years. The Federal Ministry of Power announced that the equipment, which includes transformers, cables, and switchgear, has been cleared for deployment to strengthen the national electricity grid. This development follows a directive from President Bola Tinubu for the immediate clearance of the cargoes and the resolution of outstanding administrative bottlenecks.

Speaking in Lagos, Power Minister Joseph Tegbe announced the unblocking of shipments, specifying that 44 units emerged from the ENL Terminal while another 54 came from the APMT and Sun & Moon facilities. Over 300 containers remain detained at the harbors, and authorities are actively pursuing the liberation of the additional 200-plus units still held. Acquired to boost grid capacity and alleviate strain on congested substations, the machinery’s extended impoundment has hindered vital infrastructure development.

Background

The transmission equipment had been detained at Nigerian ports for nearly two decades, a period that the Ministry of Power described as causing significant strain on the power sector. The delay kept existing substations under heavy load, exposed valuable national assets to deterioration, and resulted in the accumulation of demurrage and other charges. According to the ministry, the cost of this delay was borne by Nigerians, including businesses that incurred higher costs for alternative power sources and households that faced frequent power interruptions.

Following an inspection, officials determined that most of the equipment remained useful and viable. The release was facilitated by the Nigeria Customs Service (NCS), acting on the President’s directive. Customs Comptroller-General Bashir Adeniyi reported that the agency has initiated clearance procedures in partnership with the Power Ministry, the Nigerian Ports Authority (NPA), and the terminal management companies. He committed to coordinating with the Power Ministry until every pending container is processed and urged terminal managers to assist in this national endeavor.

Minister Tegbe credited President Tinubu for the breakthrough and acknowledged the contributions of several government officials. Gratitude was extended to Finance Minister Taiwo Oyedele, Marine and Blue Economy Minister Adegboyega Oyetola, the Customs Comptroller-General, along with representatives from the Nigerian Ports Authority and the Power Ministry. The government did not provide specific details on the initial reasons for the customs detention, but noted that the release followed the resolution of outstanding charges and administrative issues.

Why it matters

The deployment of this equipment is expected to address critical infrastructure constraints in Nigeria’s power sector. By completing stalled installations and strengthening constrained transmission corridors, the government aims to reduce the pressure on overloaded substations. This is anticipated to improve the voltage profile and result in fewer power interruptions for homes, businesses, and essential public services. The department indicated that the machinery will undergo inspection, testing, and necessary repairs prior to its installation at the designated project locations. The release is viewed as a significant step toward improving the reliability of electricity supply across the country, addressing a long-standing issue that has affected economic activity and daily life.

What happens next

The Ministry of Power has assured the public that it will oversee the recovery process through to installation and inauguration. The ministry plans to provide regular updates on the status of the remaining containers, expressing confidence that they will be released without further delay. Engineers are currently tasked with verifying and testing the released equipment to ensure it meets operational standards before deployment. Authorities are persisting in their attempts to free the remaining 200-plus containers, with the goal of finishing the grid expansion as initially planned.

Sources

Spotted an error? Report a correction · Corrections policy

#nigeria#power sector#energy#infrastructure#customs

Related stories

Nigeria launches $78.5bn private‑capital drive for 65 infrastructure projects
Africa/Nigeria

Nigeria launches $78.5bn private‑capital drive for 65 infrastructure projects

The federal government presented a $78.5 billion investment programme covering 65 projects in energy, transport, agriculture and other sectors, aiming to attract private funding and create hundreds of thousands of jobs.

LAS News Desk · 15 Oct 2026, 04:15 WAT · 2 sources

Four new transmission substations commissioned in Kano, adding 544MW to the power grid
Africa/Nigeria

Four new transmission substations commissioned in Kano, adding 544MW to the power grid

The Federal Ministry of Power and the Transmission Company of Nigeria commissioned four transmission substations in Kano State, increasing grid capacity by 544 megawatts and aiming to ease overloads and serve industrial, commercial and residential users.

LAS News Desk · 25 Oct 2026, 16:15 WAT · 3 sources

Transmission Company of Nigeria refutes Ikeja Electric’s claim that grid instability caused recent Band A outages
Africa/Nigeria

Transmission Company of Nigeria refutes Ikeja Electric’s claim that grid instability caused recent Band A outages

The Transmission Company of Nigeria (TCN) said the Band A feeder outages recorded on 3‑4 November were due to reduced generation from gas‑fuelled and hydro plants, not grid instability, and criticised Ikeja Electric’s public notice as misleading.

Photo: Godmyhelper / Wikimedia Commons · CC BY-SA 4.0

LAS News Desk · 6 Nov 2026, 22:15 WAT · 6 sources

Apapa Customs earns N302bn in October, up 7.13% from September
Africa/Nigeria

Apapa Customs earns N302bn in October, up 7.13% from September

The Apapa Area Command of Nigeria Customs Service collected N302.95bn in October 2026, a rise of N20.16bn over September, marking a 7.13% month‑on‑month increase and the third time the command surpassed the N300bn threshold.

LAS News Desk · 5 Nov 2026, 15:46 WAT · 2 sources

President Tinubu greenlights Ibom Deep Seaport after Governor Eno’s appeal
Africa/Nigeria

President Tinubu greenlights Ibom Deep Seaport after Governor Eno’s appeal

President Bola Tinubu approved the Ibom Deep Seaport project in Akwa Ibom State during an APC rally in Uyo, citing its potential to boost South‑South economic development, after Governor Umo Eno pledged two million votes for his 2027 re‑election bid.

Photo: Chatham House / Wikimedia Commons · CC BY 2.0

LAS News Desk · 7 Nov 2026, 06:38 WAT · 7 sources

President Tinubu orders clearance of over 300 containers of stranded power equipment in Nigeria
Africa/Nigeria

President Tinubu orders clearance of over 300 containers of stranded power equipment in Nigeria

President Bola Tinubu has directed the Ministry of Power to work with the Nigerian Ports Authority and Customs to release more than 300 containers of electricity equipment that have been held at ports for up to two decades, as part of a broader push to expand transmission capacity.

Photo: Chatham House / Wikimedia Commons · CC BY 2.0

LAS News Desk · 29 Oct 2026, 04:16 WAT · 2 sources

More Africa/Nigeria news ›

Get the LAS News briefing

The day's top stories from Nigeria, Africa and the world, in your inbox.